The project
The project’s scope of work includes the engineering and construction, and operation and maintenance of a groundwater treatment facility capable of removing PFAS and nitrate during a dewatering project. Flow rate measured 300m³/hour.
Scope of the services
Detailed engineering of the installation (including the set up of the installations, pump and piping design, P&IDs).
Installation of the modular system, consisting of four (4) parallel and similar treatment lines with a capacity of 75 m³/hour each. Each line consisting of:
Remote and continuous process control and data collection
Construction of a system for re-infiltration of the treated waterTwo years upkeep, service and maintenance
Project data
Project Location: Frankfurt, Germany
Executed by: Hoelscher Wasserbau GmbH
Contact Person: Lars Steijn ( lsteijn@tjaden.nl)